PROJECT DESCRIPTION
Engineering, procurement, and construction of a 50 MWp solar plant and grid interconnection works including 8 km 22 kV buried cable and one substation 22/220/kV with 125 MVA TF, and operation and maintenance for five years.
- location: Zafarana, Egypt
- Client: New & Renewable Energy Authority (NREA)
- Scope: Engineering, Procurement, Construction, Operation, Maintenance
- Duration: 12 Months
- Date of completion: October 2022